On the 19th Of May this year, the DCE of Breman Asikuma District, Hon. Lawrence Edutuah-Esiaw together with, Hon. Ransford Kwesi Nyarko of Ajumako Enyan Essiam District and some officials from the Ghana Highway Authority (GHA) as well as Ariyan Ghana Limited, the firm responsible for the construction of the 20km Ajumako to Asikuma road embarked on a joint site inspection and a meeting over the progress of work on the road.
As at the time of the inspection it was noted that 30% of the work has been completed and the date of completion is expected to be in September 2024.
The Ghana Highway Authority informed us that all is set for the construction of Bisease-Bedum-Asikuma road.